Building the Substructure
The substructure
is the supporting part of a bridge. For
this project there are five piers and, of course, two abutments. The piers will be built first. This process is usually: build a cofferdam
and pump the water out, drive the piling, pour the footing, pour the column,
and pour the pier cap.
Pouring the pier column Setting the forms First Pier Complete
Pile Driving Insulated Forms Second Pier Complete
Building the Cofferdam Rebar stockpile Five Piers